URDF Roscommon Town Centre East Public Realm Enhancement Project
Christmas 2026 Project Update
As the Christmas period approaches, Roscommon County Council would like to thank residents, businesses, visitors and road users for their continued patience and support while works progress on the Roscommon Town Centre East Public Realm Enhancement Project.
Significant progress has been made in recent months, and every effort is being made to facilitate access throughout the busy Christmas trading period.

Works Progressing Before Christmas
Athlone Road
- Road carriageway resurfacing works are ongoing with road marking & ironwork adjustment to be completed.
- The Athlone Road will fully re-open to traffic on Saturday 28th November 2026.
Goff Street Lower
- Goff Street Lower will re-open to traffic by close of business on this Monday 30 November with the new permanent one-way traffic arrangement coming into operation, with traffic travelling in the outbound direction from the town centre.
Henry Street
- Henry Street will close on Tuesday 1st December 2026 to facilitate works on the project.
- The street will remain closed until 18th December 2026, when it will reopen for Christmas.
- Access to St Comans Church carpark will be maintained.
- Ongoing access for residents and arrangements for business deliveries will be maintained throughout the works.
Circular Road
- Public realm works at various locations along Circular Road will continue up to 18th December 2026 with vehicular access being maintained at all times.
- Pedestrian access will be maintained on at least one side of the road, with signed crossing points provided where necessary.
- The new carpark at the rear of the Arts Centre is now fully open & available for use
Christmas Shutdown Arrangements
To support the Christmas trading period and minimise disruption, all construction activities within the town centre will cease from 18 December 2026 until 4 January 2027. During this period:
- Unrestricted vehicular access to Main Street and The Square via Athlone Road and Goff Street will be available.
- Full pedestrian access throughout the town centre will be restored.
- Businesses, residents and visitors will be able to access the town centre as normal during the Christmas season.
Works Restart in January 2027
Works will recommence on 4th January 2027, with construction activities resuming at planned locations within the town centre as the project continues into its next phase.
Supporting Christmas Trading
Roscommon County Council would like to reiterate that the town remains fully open for business. The temporary traffic management measures being implemented are intended to ensure that residents, visitors and shoppers can continue to access Roscommon Town safely and conveniently while this transformative regeneration project is being delivered.
As normal, car parking across Roscommon Town remains free of charge, with all public car parks open and available for use.
The Council would like to sincerely thank everyone for their continued patience, understanding and cooperation as these important improvements progress.
The local authority encourages the public to continue supporting local businesses throughout the Christmas and New Year period and to enjoy all that Roscommon Town has to offer during the festive season.